2 Proposed Timeline
The dates for the Market System User Group Meetings (MSUG Market Systems User Group) are tentative. We will provide an invitation one week prior to the meeting.
Milestone |
Date |
Description |
---|---|---|
Approval required |
n/a |
Final date for participant approval of this Release Published date + 15 business days from final release schedule |
Revised Technical Specification |
TBC |
AEMO releases new versions of this document as the technical requirements are streamlined. During the project this document is the source of truth. From the pre-production release, the technical specification is no longer updated, the related documents become the source of truth. |
Related Documents publication |
Wednesday 9 October 2024 |
Release of guides and resources mentioned in 1.8 Related documents |
Next MSUG meeting |
Wednesday 13 November 2024 |
Market Systems User Group Meeting (MSUG) to review the technical specification and ask AEMO technical SMEs questions. This date is tentative. The project manager will provide an invitation one week prior to the meeting |
Pre-production Data Model auto subscription |
9 October 2024 No auto-subscription for existing files. |
For any existing files with modified or new tables, if participants are subscribed, AEMO moves them to the Legacy version For more details, see 3.1 Electricity data model v5.4 |
Pre-production Data Model release |
Wednesday 9 October 2024 |
Participant Data Model scripts released |
Pre-production refresh |
1 July 2024 – 5 July 2024 |
Refresh of the pre-production system with data refreshed from the production system. An outage of up to five days can occur to the pre-production environment during this period. Participant access is not restricted, however, AEMO do not guarantee the pre-production data content or system availability. During the refresh, access to other AEMO systems such as AWEFS, EMMS, OPDMS, and STTM may be intermittently affected |
Pre-production implementation |
Wednesday 9 October 2024 |
AEMO implements components of the Release to pre-production for participant testing AEMO has full access to the system during this period Participant access is not restricted; however, the data content or system availability is not guaranteed |
Pre-production available |
Wednesday 9 October 2024 |
Testing period begins for participants |
Participant Testing |
Wednesday 9 October 2024 – Wednesday 6 November 2024 |
Unstructured/bilateral participant testing in the pre-production environment |
Production implementation |
Wednesday 6 November 2024 |
AEMO implements the release to production |
Production Data Model auto subscription |
Wednesday 6 November 2024 No auto-subscription for existing files |
For any existing files with modified or new tables, if participants are subscribed, AEMO moves them to the Legacy version For more details, see 3.1 Electricity data model v5.4 |
Production Data Model release |
Wednesday 6 November 2024 |
Participant Data Model scripts released |